Journal of the International Academy for Case Studies (Print ISSN: 1078-4950; Online ISSN: 1532-5822)

Case Reports: 2024 Vol: 30 Issue: 2

The Revamping of Lahore General Hospital

Tayiba Ashraf, Superior University Lahore

Muhammad Rafiq, Superior University Lahore

Citation Information: Ashraf, T. & Rafiq. M (2024). The revamping of Lahore general hospital. Journal of the International Academy for Case Studies, 30(2), 1-7.

Abstract

Rafaqat the project executive Engineer, the project head of Revamping of Lahore General Hospital byCNW1 observed that Lahore General hospital building had surpassed its design life and with the passage of time haphazard constructions were obstructing the flow of patients. Secondly the earlier constructions were not in good condition which were damaged from time to time. Sometimes hospitalwas deprived of one facility and sometimes it was deprived of another facility. Work wasn’t doing the proper planning. Provision of quality secondary healthcare services to all sections of society across Punjab has been among the top priorities of provincial governments. The government not only took several measures to improve the condition and environment but also improved the medical services provided by these hospitals. Among these initiatives, the revamping program can be cited as the representative initiativeof the government to reform the health care sectorinPunjab. The revamping project for Lahore GeneralHospital was initiated by CNW, Government of Punjab.

Rafaqat the project executive Engineer, the project head of Revamping of Lahore General Hospital by CNW1 observed that Lahore General hospital building had surpassed its design life and with the passage of time haphazard constructions were obstructing the flow of patients. Secondly the earlier constructions were not in good condition which were damaged from time to time. Sometimes hospital was deprived of one facility and sometimes it was deprived of another facility. Work wasn’t doing the proper planning.

Provision of quality secondary healthcare services to all sections of society across Punjab has been among the top priorities of provincial governments. The government not only took several measures to improve the condition and environment but also improved the medical services provided by these hospitals. Among these initiatives, the revamping program can be cited as the representative initiative of the government to reform the health care sector in Punjab. The revamping project for Lahore General Hospital was initiated by CNW, Government of Punjab.

Background

A beggar home was suggested for a plot of land of 256 Kanals, on Firozpur Road in Lahore, which is around 17 kilometers from Lahore (Annexure 1, Figure 1). On February 27, 1958, Her Excellency Begum Naheed Sikandar Mirza, W/O, Governor General of Pakistan, lay the foundation. The building's initial section was finished in late 1958. On September 30, 1958, Her Excellency Begum Naheed Sikandar Mirza presided over an inauguration ceremony. The intended Beggar House Plan was abandoned for many reasons, and the government at the time chose to offer health services to everyone. Thus, in the early months of 1959, Lahore General Hospital was established.

On January 29, 1959, His Excellency MR. AKHTAR HUSSAIN, the Governor of West Pakistan, performed the Lahore General Hospital inauguration ceremony. LGH2 began operations in the intended Beggar House's existing facility. At the time, Lahore General Hospital lacked enough treatment and diagnostic capabilities, hence the hospital was utilized as a convalescent home for Mayo Hospital, Lahore overflow patients.

In 1966, Lahore General Hospital became the home of King Edward Medical College's Neurosurgery department. Up until 1981, this department was briefly situated in an ancient structure. Subsequently, in July 1975, Lahore General Hospital Lahore became a part of Postgraduate Medical Institute Lahore following its establishment in 1974.

With the exception of the neurosurgery, T.B3., and chest departments, which were still affiliated with the K.E.M.C.4 in Lahore. New physiotherapy and neurosurgery departments were finished in April 1984, and it was moved into a new structure called the neurosurgery block. When Allama Iqbal Medical College moved to a new site in 1995, PGMI5 was moved to Services Hospital in Lahore and the Jinnah Hospital complex became a part of AIMC6. AIMC was connected to the main hospital located in Lahore. This persisted until May 31, 1997. Subsequently, on May 31, 1997, LGH was once more connected to PGMI. All of these departments, including the neurosurgery department, are currently a part of PGMI Lahore. LGH was designated as an autonomous hospital on July 1st, 1998. The hospital's first chief executive officer was selected to be Dr. Sabiha Khurshid Ahmad. Following autonomy, the tremendous weight of SOT7 was reduced by the opening of additional, well-equipped urology and orthopaedic operating theatres. Additionally, SOT underwent renovations and a new recovery room was constructed. Additionally, a washing plant was set there. Apart from the eighteen rooms in the Neurosurgery Department, seven rooms have been designated for private patients on the general side.

A Strategic Decision to Revamp

The Government of Punjab observed the condition of the hospital and Govt. approved a plan to improve the treatment and other facilities at the Lahore General Hospital of the province to provide better health facilities to the people. In September 2023, the Revamping Project of LGH was initiated by the Rafaqat Ali executive engineer of 3rd building division Lahore from CNW Department of the Government of the Punjab as a project head. The Health Department was funding the project. IDAP8 was responsible for planning and designing the project (Annexure 2, Figure 2 & Figure 3). The main aim of the project was to address a plethora of shortcomings of the healthcare in the province and dire need of complete revamping and re-planning. Prior to this project, healthcare service delivery was marred with 4 essential problems, which was directly affecting the efficacy and operational efficiency of LGH. These problems included the following:

Infrastructural Problems

Considering that LGH was constructed in varying degrees over the years, most of the buildings were in a dilapidated condition. Over the years, weathering has reduced the overall strength and safety of the buildings. Leakage and drainage problems and the general dilapidation of the buildings created a very uncomfortable environment for patients, and in addition, made for poor hygiene and infection control.

Unavailability of Bio medical gasses

It is an indisputable topic how important oxygen is for patients in hospitals. Not only oxygen but also many other biomedical gases required in hospital should be available in adequate quantity. And it was not available in adequate quantity in LGH. Nor was it available at every patient's bedside.

Poor Allied Services of OT

While clinical services are key in any hospitals “functioning”, it’s the Allied Services that ensure smooth operations. Good hygiene practice is essential in hospitals and operating theatres. But at the LGH operation, the theaters were in poor condition and were not being hygienically controlled.

Poor Hospital Processes

Critical to the functioning of any hospital, the hospital's ability to employ and maintain critical standardized clinical processes that help streamline patient records, ensure IT solutions for proper data management and implements a quality assurance system whereby a high level of service delivery is maintained. which was not working effectively in LGH.

Based on these observations and after a deep-dive into each problem, it was decided that a 4-point agenda of revamping would be designed that would deal with each of the problematic areas and create an overall effective healthcare service delivery regime, that would be standardized across any hospital that would come under the “Revamping” project. This package was designed as follows:

Infrastructural Development

Under this agenda, renovation of existing hospital buildings, establishment of new special care units, provision of electricity and other necessary utilities, and an overall improvement of the hospitals environment through soft interventions was carried out.

Availability of Bio Medical gasses

To ensure the quality of healthcare services was standardized, it was necessary to provide good quality equipment to LGH. Uniformity of IDAP across the board ensured that medical bio gasses services would be available to every patient. This included equipment such as oxygen, nitrogen other necessary biomedical and non-biomedical equipment.

Modernization of Operation theater

To ensure that all services can be delivered quickly, and consider the scale of impact of reaching as many people as possible. Modernization of 17 operation theatres including antibacterial/antistatic flooring, PVC9wall cladding, automatic hermetic sliding sealed hinged door, peripheral lights LED, dimpa ceiling, surgeon control Operation theater etc. A constructive and functional and personal hygiene survey was conducted in all the operating theatres of the hospitals.

IT Interventions

These included establishment of QMS10 that would ease a patient’s journey through the hospitals and record documentation necessary for medical histories. Team CNW worked on Supply and erection of PVC pipe for wiring, Installation of gang plates,3-pin switch and plug, MCB11 and MCCB12 breakers etc.

As the Project timeline fixed by govt. of Punjab was 22 Oct 2023 to 22 Feb 2024 as per their scope of work (Annexure 3, Table 1). And Govt. allocated a budget of a Rs 1 billion13 for the hospital upgradation/revamping. After 4 months the budget collapse due to the interim government which caused delays in payments to contractors and delays in work. And reauthorization took 20 to 25 days, due to which their development was affected.

Operational Discussion and its Chalegnes

After this stage their main function was bidding/pre-qualification. A bid is an offer made by a contractor to a client in order to win a construction project. A bid includes an estimate of the cost of labor and materials necessary to complete the project, as well as a proposed timeline for completion. To ensure better selection of contractors, Project Head invited the vendor/contractor for Bid/pre- qualification through newspapers from 22-9-2023 to 27-9-2023. The project was divided in to three group;(Annexure 4, Figure 4)

OPD block Phase I & OPD block III

In the first group, were selected for revamping which included civil Roof Top Treatment, Dismantling of Tiles, Removing of Ceiling, Dismantling of Tiles, Scraping Work, Removing of Doors and Windows. Total funds of Rs. 241.760 Million14 were provided to where work was at different stages of its completion.

Old Surgical Wards & OPD block Phase II

In the second part, were selected for revamping which included civil Roof Top Treatment, Dismantling of Tiles, Removing of Ceiling, Dismantling of Tiles, Scraping Work, Removing of Doors and Windows. Total funds of Rs. 241.760 Million15 were provided to group 2.

Emergency Block

In the first part, were selected for revamping which included Dismantling of Tiles, Ceiling, Removing of Doors & Windows and Scraping Work, Brickwork, Plastering. Total funds of Rs. 237.341 Million16 were provided to group 3. He made certain criteria for pre-qualification based on their company registration, their financial soundness, relevant experience, personnel skills and equipment & machinery capacity etc. Those who matched the criteria were eligible and those who were disqualified went to litigation which was a challenge to them. His legal department explained to court all pre-qualification processes where the participant did not meet their criteria and completed all court proceedings. He settled this court case before the project. On 21st October 2023 he selected 3 best contractors and allotted them work order for 5lakhs ft. (Annexure 5, Table 2).

He discussed the Hospital administration that the pre- qualification plan already been completed and tenders have been called on 21 OCT 2023. The contractors will be immediately mobilized keep in you the timeline if the project. However, the hospital is still functional and no building has been evacuated so far, project might suffer delay if buildings are not evacuated at earliest. The administration of LGH raised their concern over complete vacation of the buildings, administration pointed out that current influx of public in the hospital is about one hundred fifty thousand (150,000) person per day. It’s not possible in practical for us to evacuated the whole hospital at a time then Administration of the hospital discuss about the alternative plan that administration will evacuate the emergency department completely and will excavate the rest of the department by phases/floors. He agreed on it because their main target was the emergency. He evacuated 100% of the basement of the emergency block and 30% to 50% of the rest of the building and started their work from October 22, 2023 as per the schedule keeping in mind the patent flow (Annexure 6, Figure 5).

Project Leader Rafaqat divided the work into two shifts. One from 8AM to 4PM, the other from 4PM to 12PM. IDAP created and distributed drawings of revamping areas to clients and took periodic updates with all departments regarding the scope of work. Scope of work floors of all the buildings Project head team intend to renovate team was working, team faced more damage in it. After considering several approaches, he decided to issue a challenge to the hospital's administration, IDAP and with his team to identify ways to achieve RS. 7 million improvements in the hospital's bottom line.

After that he went for procurement of all buildings material then Project head faced another challenge that there is no bulk material in the market because at the same time this concept of Punjab Govt. started in other hospitals so demand was increased due to shortage of supply. So, Project head chose a different vendor to improve their supply chain. Who used to supply them with special materials and due to this most of the factories got work and started production in high volume which created employment opportunities for various people. After that, he realized that many things like bumper rail he couldn’t get manufactured here as it is not manufactured in our local industries. So, he decided to import it from Europe but in that case he faced another challenge that in December, there is usually holidays in Europe due to Christmas, so he had to ordered the material before that and ensured that all their shipments moved there so that vender could be delivered in January 2024. Then Project head will be able to implement it in January when project is close to completion. The operation team will monitor the progress of the project and will hold regular weekly meeting to review the progress under the supervision of Rafaqat Ali.

Outcome

This revamping is a good initiative that will bring some tangible improvements in hospital operations and service delivery. In particular, the non-medical functions of the hospital (administration, human resource management, procurement and audit, stock and logistics, etc.) and services (laboratory, bio medical gasses, sanitation, hospital waste management, infection control, etc.) and the patient flow will be significantly improved. And the public hospital will be more attractive like the private hospital.

Conclusion

Revamping in the LGH will improve the overall quality of healthcare service in hospital. It appears that the facilities provided to the public at secondary level have increased the trust of general public towards public health facilities. This assertion will substantiate with the rise in the number of OPD patients in LGH of revamping project in a year. It could be anticipated that this intervention may contribute to further increase patient load at secondary level and lesser patient turnover at tertiary level healthcare facilities. This trend is encouraging and gives the resource constraints at the tertiary level, it is of paramount importance that patients are homogenously distributed across the three health tiers.

Annexure 1

Figure 1 Map

Annexure 2

Figure 2 Exisiting Design

Annexure 3

Table 1 Timeline Table
Month October November December January February
Days 1 to 21 22 to 30 1 to 15 16 to 30 1 to 15 16 to 30 1 to 15 16 to 30 1 to 15 16 to 22
Description of Item/ Activity                    
Award of work                    
Dismantling Activities                    
Tile laying (floor, dado, ramp)                    
Petty     repair     to rooms, verandah, washrooms                    
Doors/Chowkat fixing                    
Washroom UPVC and PPRC supplying                    
False ceiling                    
Electrical wiring                    
Installation of Doors & Windows                    
Paintwork                    
Fitting of washroom accessories                    
Fixing of plates, sockets, switches, lighting                    
Roof insulation and treatment                    

Annexure 4

Figure 3 Proposed Design

Annexure 5

Table 2 Area
Buildings Basement Ground Floor First Floor Second Floor Third Floor Fourth  Floor Total
Emergency 20,400 15,471 15,471 15,471 15,471   82,284
Surgical Wards   51,560 19,475 22,000     93,035
Phase 1   20,250 48,440 19,476 19,477   107,643
Phase 2   48,250 48,250 47,450 47,450 19,100 210,500
Phase 3   11,500 11,500 11,500 11,500   46,000

Annexure 6

Figure 4 Revamping Blocks

End Notes

1Communication and work

2Lahore General Hospital

3Tuberculosis

4King Edward Medical University

5Post graduate Medical Institute

6Allama Iqbal Medical College

7Sacro-occipital Technique

8Infrastructure Development Authority of the Punjab

9Polyvinyl Chloride

10Que Management Systems

11Miniature Circuit Breakers

12Molded Case Circuit Breakers

13$3499868.71

14$858689.03

15$858689.03

16$844436.93

Received: 23-Jan-2024, Manuscript No. JIACS-24-14408; Editor assigned: 25-Jan-2024, Pre QC No. JIACS-24-14408 (PQ); Reviewed: 12-Feb-2024, QC No. JIACS-24-14408; Revised: 20-Feb-2024, Manuscript No. JIACS-24-14408 (R); Published: 01-May-2024

Get the App